BHAGIRATHA WORKS... SNAIL WALK IN TWO MANDALS

 

Nalgonda,May 10,(globelmedianews.com):
Mission Bhagiratha Scheme is underway at Motkuru and Addaguduru Mandalas. The construction of water tanks in the scheme is undergoing months. Some of the tanks did not get started, but the performance of this scheme is known. The construction of pipelines is in disarray. Potholes are dug in areas where people walk. This is going to cause difficulties. There are 12 gram panchayats in Mothkur mandal, 16 gram panchayats in Addaguduru mandal and some villages have not been constructed. Construction of pipelines and construction of tanks will be done by the construction of the indigenous pipelines in villages. They claim that it is possible to provide the house with the installation of the house. Locals want to be in touch with senior officials in order to complete the construction of timely structures. 


BHAGIRATHA WORKS... SNAIL WALK IN TWO MANDALS

The Rs.5.4 crore in Mudkur mandal in July last year and Rs 5.9 crore in Vadakadu mandal is to be completed by the end of June. 22 tanks were sanctioned and 18 tanks were constructed. Five of these tanks are complete, and four tanks are not under construction. The tanks were sanctioned and 19 tanks were sanctioned and 13 tanks were started. Yet six tanks do not start work. The construction of the remaining tanks is underway. Water curing is not doing properly due to the construction of tanks during the summer. The locals criticize the construction of pillars at many tanks. Mistresses do not work properly because of the sun. Due to the fact that the monopolist does not work, the work does not work properly.

No comments:
Write comments